• Rock Tech Lithium (RCK) has provided an update on the progress of the test work and engineering development for its Georgia Lake and Converter projects
  • The phase 1 pilot plant at ALS is fully operational
  • Crude Lithium Hydroxide crystallization is currently in progress and a final purified Lithium Hydroxide sample is anticipated in May
  • Work is ongoing with ALS Laboratories, with purification and causticization work completed
  • Heavy Liquid Separation (HLS) and Dense Media Separation (DMS) work has been completed on core samples from Georgia Lake
  • Rock Tech Lithium Inc. is a lithium development and chemical technology
  • Rock Tech Lithium is up 6.44 per cent, trading at C$4.79 per share at 11:15 am ET

Rock Tech Lithium (RCK) has provided an update on the Phase 1 pilot plant, testwork and engineering for its Georgia Lake and Converter projects.

The phase 1 pilot plant at ALS is fully operational. Lithium hydroxide samples from the bench-scale metallurgical test work program are expected in May.

The metallurgical test work program supports basic engineering development for the converter project and the Phase 1 pilot plant.

Converter Metallurgical Testwork Program

To support the basic engineering development for the converter project and inform the phase 1 pilot program, a metallurgical test work program has been ongoing since December 2020. Nagrom laboratories was appointed to complete a bench-scale test work program under management by Wave International.

The program was designed to prove the robustness of the flowsheet to produce battery-grade Lithium Hydroxide from a range of spodumene sources. Coarse DMS concentrate, low-grade DMS concentrate, and combined DMS and flotation concentrate samples from various global sources are part of the test work program.

The test work program for the conventional sulphation route has progressed through the unit process of calcination, acid roast, water leach and impurity removal, causticization and Glauber’s salt crystallization on the three different samples.

Crude Lithium Hydroxide crystallization is currently in progress and a final purified Lithium Hydroxide sample is anticipated in May.

This work informed the Phase 1 pilot underway at ALS and will inform an upcoming stage 2 pilot, as well as provide engineering data for ongoing engineering development.

Figure 1 – Glauber’s Salt Precipitation Test

Nagrom, a privately owned Western Australian company, has been providing metallurgical services to the mining industry for over 30 years. Their Kelmscott facility has over 100 processing units and a staff of 120 skilled resources. Nagrom is a recognized brand in the Lithium sector, with extensive spodumene and downstream lithium test work experience across major and emerging producers.

Phase 1 –Lithium Hydroxide Monohydrate Bulk Sample

Work is ongoing with ALS Laboratories, with purification and causticization work completed. The next stages of the works are Glauber’s salt crystallization, followed by crude Lithium Hydroxide crystallization.

All testwork to date has performed as expected by the PFS conventional flowsheet and per the bench-scale testwork program. The final purified Lithium Hydroxide sample from the Phase 1 pilot plant is anticipated to be produced by June 2021.

The lithium hydroxide samples produced during the metallurgical testwork program and the phase 1 pilot will be used to intensify offtake discussions with potential customers.

Georgia Lake Lithium Project

Heavy Liquid Separation (HLS) and Dense Media Separation (DMS) work has been completed on core samples from Georgia Lake.

Nagrom laboratories was appointed to complete this testwork program, under management by Wave International.

The testwork program was designed to test composites of different lithological classifications across a range of processing parameters. In addition to contributing to the testwork program for further studies on the Georgia Lake Lithium Project, it generated concentrate for the converter metallurgical testwork program.

Rock Tech Lithium Inc. is a lithium development and chemical technology.

Rock Tech Lithium is up 6.44 per cent, trading at C$4.79 per share at 11:15 am ET.

More From The Market Online

Adyton to recommence work at its Feni Island Project

Adyton Resources (TSXV:ADY) gears up to restart work activities at its Feni Island Gold-Copper Project in Papua New Guinea.

This company starts production at what could be Canada’s next great gold mine 

IAMGOLD (TSX:IMG) is a Canadian-based intermediate gold producer and developer focused on mining properties in North America and West Africa.

Teck misses Q1 profit estimates on lower steelmaking coal sales

Canadian mining stock Teck Resources Ltd. (TSX:TECK.A and TECK.B; NYSE:TECK) misses Q1 profit estimates on Thursday.
The Market Online Video

Exploration company provides project portfolio update

Banyan Gold Corp. (TSXV:BYN) is focused on exploration and advancing and de-risking its AurMac Gold Project in the Yukon.