• The fully modular Molo graphite processing plant has arrived in Madagascar, been unloaded and is now in transit to the mine site
  • Commissioning of the mine is on schedule for the fall of 2022 making NextSource’s Molo mine the only graphite project to come into production this year outside of China 
  • Construction of the solar thermal hybrid energy power plant that will power Phase 1 of the Molo mine will be completed when the mine commissions
  • Brent Nykoliation, Executive Vice President of NextSource, sat down with Daniella Atkinson to discuss the news
  • NextSource Materials is a Canadian-based strategic materials development company
  • NextSource Materials Inc. (TSX:NEXT) opened trading at C$3.11

NextSource Materials (NEXT) has provided a progress update for Phase 1 of the Molo Graphite Mine in Madagascar.

The processing plant has been unloaded at the local port of Fort Dauphin in Madagascar and has cleared customs. Company-appointed logistics specialists have now commenced transporting all modules of the plant, including two mobile cranes, to the mine site. Earthworks at the mine site are complete and civil works are on schedule to be completed by the time the Processing Plant arrives.

It is expected to take approximately 45 days to re-assemble the processing plant, which underwent Factory Acceptance Testing prior to shipment. Once re-assembled, it will undergo Site Acceptance Testing, which is the final step before mine commissioning.

The pre-fabricated units for the camp accommodations and auxiliary buildings have also arrived on site and assembly of these support structures will commence shortly.

Brent Nykoliation, Executive Vice President of NextSource, sat down with Daniella Atkinson to discuss the news.

https://storage.googleapis.com/accesswire/media/711353/PHOTO-2022-08-08-11-57-50.jpg

CrossBoundary Energy’s Madagascar subsidiary commenced construction of a solar thermal hybrid energy power plant that will power Phase 1 of the Molo mine. Construction of the Hybrid Plant is on schedule with the thermal portion of the hybrid solution expected to be installed and operational at the time of commissioning of the Processing Plant, with the renewable energy portion following thereafter.

The hybrid plant will be located adjacent to the Molo mine site and when fully operational, will provide up to 33 per cent of the mine’s total Phase 1 electricity needs from renewable solar energy, with the remainder coming from thermal generators.

NextSource Materials Inc. is a Canada-based strategic materials development company. NextSource is driven to become a fully integrated, global supplier of critical battery and technology materials needed to power the sustainable energy revolution.

The company’s Molo graphite project in Madagascar is one of the largest known and highest-quality graphite deposits globally, and the only one with SuperFlake graphite.

NextSource Materials Inc. (NEXT) opened trading at C$3.11.


More From The Market Online

@ the Bell: TSX keeps it just above the flatline

Driven by materials stocks tracking higher metals prices, utilities led gainers on the TSX while energy and industrials led the drop.
Negotiating in a meeting room

Grid Battery Metals sets spin-off date for AC/DC Battery shares

Grid Battery Metals Inc. (TSXV:CELL) reveals April 25, 2024 as the date for distribution of AC/DC Battery Metals' common shares.
Arizona Metals - The Kay Mine gold and copper project in Arizona.

Multi-bagger penny stock announces high-grade expansion

Arizona Metals, a multi-bagger penny stock, announces high-grade results from expansion drilling at its Kay Mine project in Arizona.

Silver Spruce launches drilling program in Mexico

Silver Spruce Resources (TSXV:SSE) announces it has begun its 2024 drilling program at the Diamante project in Mexico.