  • Fortuna Silver Mines Inc. (FVI) has achieved construction and operational milestones for its Séguéla Gold Project in Côte d’Ivoire
  • The overall project is approximately 90 per cent complete
  • It remains on-track, and on-budget for its first gold pour in mid-2023
  • The next stage of mining equipment is on-schedule for late-February availability and some mining preparations have already started
  • Fortuna Silver Mines Inc. (FVI) is up 3.11 per cent, trading at $5.30 per share as of 3:12 p.m. EST

Fortuna Silver Mines (FVI) has achieved construction and operational milestones for its Séguéla Gold Project in Côte d’Ivoire.

The overall project is approximately 90 per cent complete and remains on-track and on-budget for its first gold pour in mid-2023. Commissioning of the fuel depot and grid connection and energization of the substation for the project is complete.

David Whittle, COO in West Africa for Fortuna Silver Mines, commented,

“Our operational teams are being assembled with an experienced core leadership group already hired… This will mark a significant milestone for Fortuna, with Séguéla also exhibiting growth potential given the quantity of inferred resources and the exploration success on the property to date.”

The company’s operational readiness has become the focus in preparation for the commissioning of the processing plant. As a result of the site team’s work, the project is ready for this transition which also represents a significant milestone for the company.

The project’s mining contractor has established its temporary facilities on site to support initial mining activities, with construction of the permanent mining services area infrastructure progressing well. The mining fleet required for initial mining activities is on site and has been commissioned.

The next stage of mining equipment is on-schedule for late-February availability. Additionally, mining preparations are underway, with the Antenna Stage one pit having been cleared and grade control drilling in progress. The pad and Antenna pit haul road areas have been cleared for construction which is scheduled to begin shortly.

Fortuna Silver Mines Inc. (FVI) is up 3.11 per cent trading at $5.30 per share as of 3:12 p.m. EST.


More From The Market Herald
Market summary - Finance Minister, Chrystia Freeland.

" @ the Bell: TSX keeps streak alive on budget day

Canada’s main stock index closed higher on Tuesday tracking gains in crude oil prices, as traders expect that the worst could be over

" SQI (TSXV:SQD) to focus on product development for respiratory health

SQI (SQD) is refocusing its business on creating precision point-of-care products in respiratory health.
The Market Herald Video

" Fuse Battery Metals (TSXV:FUSE) adds Nevada lithium exploration project

Fuse Battery Metals (FUSE) has expanded its exploration land holdings.

" H2O Innovation (TSX:HEO) details promising cartridge filter cleaning solution

H2O Innovation (HEO) has performed a cleaning-in-place for cartridge filters using its Genesys-PWT membrane cleaners.